project summary and funding request
contact: RRudder@Safe-mail.net
|
Darwin Clean Fuels is proposing to design, build and operate a condensate processing facility near Darwin's East Arm Port to produce high quality transport fuels that will meet the new Australian Standards for clean fuels.
The new processing plant will supply high quality petrol, diesel, LPG and jet fuel to the Northern Territory market. In addition, Darwin Clean Fuels will be seeking to export petrol to markets such as Asia and the US West Coast, where stringent environmental standards for fuel quality are already in place.
The Darwin Clean Fuels project capitalises on Darwin's proximity to the Timor Sea gas fields and Asia, Darwin's natural deep water port, new bulk liquid facilities at East Arm Port, the new transcontinental AustralAsia Railway linking Australia's northern and southern coasts, and the new Darwin Business Park. |



|
|
DARWIN CLEAN FUELS PTY LIMITED
Capital Expenditure Budget
PRE CONSTRUCTION COSTS BASE COST
Pre feasibility study Feasibility study and expert opinion Option on refinery site Prospectus and public company vehicle Corporate operations Design & engineering Construction contract Operation & maintenance contract Project construction & operating insurances
Conditional crude oil supply contract
Project agreement
Conditional product offtake contracts
Conditional shipping contracts |
250,000
500,000
100,000
500,000
300,000
2,000,000
50,000
50,000
50,000
50,000
50,000
50,000
50,000 |
TOTAL PRE-CONSTRUCTION COSTS 4,000,000
CONSTRUCTION PERIOD EXPENSES BASE COST
| Management |
630,000 |
| Legals |
180,000 |
| Corporate ID |
0 |
| Travel |
270,000 |
| Public relations |
360,000 |
| Office costs |
270,000 |
| Accounting |
90,000 |
TOTAL CONSTRUCTION PERIOD COSTS 1,800,000
CONSTRUCTION COSTS BASE COST
| Project Management |
12,800,000 |
| Off Plot Engineering |
2,000,000 |
| Construction Engineering |
7,400,000 |
| Process Plant Engineering |
88,200,000 |
| Refinery Installation |
20,200,000 |
| Earthworks |
5,700,000 |
| Site Security |
1,500,000 |
| Pipeline To Terminals |
1,800,000 |
| Refinery Infrastructure-Piping |
8,600,000 |
| Other Refinery Infrastructure |
23,100,000 |
| Tankage |
68,500,000 |
| Wharf |
6,000,000 |
| Power Station |
26,500,000 |
| SUB-TOTAL |
272,300,000 |
| Contingency |
27,230,000 |
TOTAL CONTRUCTION COSTS $299,530,000
TOTAL CAPEX BUDGET $305,330,000 |






|
|